Page 6 - Chief Executive Report - July 2022
P. 6

PLANNING
        ROADS                                                                                                                                                                                        appointed Consultants are

                                                                                                                               Development Management                                                currently working on this
        Major projects (Included in NDP- Funded by TII)                                                                                                                                              Masterplan and several meetings
                                                                                                                                Planning Summary                     TOTAL           TOTAL           have been held between the
                                                                                                                                                                     (April 2021)    (April 2022)    Consultants, the Planning
        N24 Waterford to Cahir Scheme                                                                                                                                                                Department and the Community
        The public consultation No 2 on Alternatives & Options is complete and the design team is working                                                                                            Section of the Council. A format
        through the submissions and commencing the preparatory work on site investigations/studies                                                                                                   for the Masterplan has been
        which will feed into the selection of the preferred corridor.                                                           Planning Applications Received       85              75              developed and the document
                                                                                                                                Planning Applications Granted        58              62              is being worked on presently. A
        Minor Projects (Not included in NDP-Funded by TII)                                                                                                                                           pre-draft draft public consultation
                                                                                                                                Planning Applications Refused        7               4               event will take place during the

        N24 Tower Road (Safety Scheme)                                                                                          Complaints Received                  51              27              last week of July.
        Approval to proceed to Phase 5 (Enabling and Procurement) has been received from TII. The                               Warning Letters Issued               47              21
        tender documentation is undergoing final cross checking and review. Once complete the formal                                                                                                 Other Towns & Villages
        request to go to tender will be submitted to TII. It is expected that the tender will be formally issued                Enforcements Notices Issued          5               11              A brief for Masterplans for
        on etenders in early August with an expectation of contractor appointed before the end of 2022.                         Cases Closed                         28              34              the settlements of Ballyraget,
        The project has a 12/15 month construction period. An allocation of €3m was received for 2022.                                                                                               Paulstown and Kilmacow has
        The overall outturn cost for the project is expected to be in excess of €10m                                           The Planning Department is open for business.  Visits to the          been prepared and placed on
                                                                                                                               Planning Office continue to be by pre-booked appointment.             etenders at the start of July. The
                                                                                                                               Appointment can be made by telephoning the planning office at         closing date for receipt of tenders
        N77 Ballyragget to Ballynaslee                                                                                         056 7794010 or by email to  planning@kilkennycoco.ie
        An allocation of €500K was received for 2022 which will fund progression to preparation of                                                                                                   is 12 noon on Friday 29th July.
        contract documents and potentially land acquisition. Approval has been sought from TII to move to                           Forward Planning              Loughmacask                        Taking in Charge
        Phase 5 (Enabling and Procurement) and is expected imminently. The overall outturn cost for the                        Masterplans:                       Work is continuing on the          Works are continuing on various
        project is expected to be circa €10m.                                                                                  Abbey Quarter                      preparation of a Masterplan        other estates:
                                                                                                                               A brief for the Abbey Quarter      for Loughmacask. An initial        •   College Park, Callan Road
        N24 Carrick Road:                                                                                                      Masterplan Review was              draft Masterplan was prepared      •   Rioch Court
        An allocation of €150K was received for 2022 which will fund progression to statutory approvals                        prepared, and published on         and was internally reviewed.       •   The Greens, Thomastown
        stage (177AE Planning Approval and Compulsory Purchase Order Approval). The formal request                             etenders in May. The closing       The Environmental Authorities      •   Kiln Lane, Callan
        from KCC to move to Phase 4 (Statutory Processes) and to publish the scheme is expected to be                          date for receipt of tenders was  were consulted in relation to        •   Castlehyde, New Ross
        submitted shortly to TII. Subject to that approval it is expected that submission of the project for                   24th June. A successful tender  environmental assessments             •   Whitehall, Paulstown
        approval to An Bord Pleanála will occur in early September 2022. The overall outturn cost for the                      has been recommended               associated with the Draft          •   Ogenty, Gowran
        project is expected to be circa                                                                                        their appointment is being         Masterplan. The concepts           •   Abbeygate, Ferrybank
        €10m.                                                                                                                  progressed.                        included in the Draft Masterplan
                                                                                                                                                                  were presented to the Kilkenny  Arbourmount, Ferrybank and Kiln
        Other Projects                                                                                                         St. Canice's                       Municipal District meeting  in     Lane, Clashacollare, Callan, Co.

                                                                                                                               The preparation of the             May.   The  final  drafts  of  the  Kilkenny have been completed
        Kilkenny Ring Road Extension                                                                                           Masterplan for the HSE’s St.                                          and are before the Council for
        Consultants have submitted the first draft (SAR) Strategic Assessment Report for review by                             Canice’s Campus is ongoing.        Environmental Assessments          taking in charge at the July
        Kilkenny County Council. The intention is for a submission to the Department for consideration to                      Loci Consultants are assisting     have now been received and         meeting.
        proceed with the design and planning in July/August.                                                                   the Project Steering Committee     are being considered. Once the     Active Land Management
                                                                                                                               in the drafting of the             iterative process of modifying     •   There are 13 sites on the
                                                                                                                               Masterplan. Draft concepts are     the draft Masterplan is finalised,     Derelict Sites (DS) Register
                                                                                                                               currently under consideration.     the draft plan and associated          at present. Notices have also
                                                                                                                               Following consultation with        documents will be placed on            been issued giving notice of
                                                                                                                               the HSE on these concepts,         public display. A sufficient length    the intent to enter further sites
                                                                                                                               a plan will be drafted. Once a     of time will be allowed for public     on the DS Register. Owners
                                                                                                                               Draft Plan is available, it will   consultation (minimum 8 weeks)         have an opportunity to make
                                                                                                                               be presented to the Council        to take account of the summer          representations on foot of
                                                                                                                               and HSE before it is placed        holiday period.                        those notices.
                                                                                                                               on public display. Public                                             •   There are 29 sites on the
                                                                                                                               display of a Draft Masterplan is   Urlingford                             Vacant Sites Register, and
                                                                                                                               targeted for commencement in       Work has commenced on the              the number of cancelled
                                                                                                                               September 2022.                    preparation of a Masterplan for        entries due to site activation.
                                                                                                                                                                  Urlingford Town Centre. The
                                                                                                           6                                                                                                                      7